Steam & Condensate Pipework - Fabrication & Installation

steam pipework.png

Project Overview

  • Isometric verification

  • 3D site scanning and closing length confirmation

  • Offsite fabrication, testing and coating

  • Site installation

  • Project Management

  • HSSE Management

  • Supervision

  • Trade Provision

  • Specialist subcontractor engagement and management

  • Testing and Commissioning

  • QA and MDR upon completion

Overview

Our client is an operator of a polypropylene production facility in Geelong, Victoria. The facility is incorporated into the Viva Refinery complex. The Client is undertaking a project to repair pipework and valves within the existing steam and condensate piping system. This includes the fabrication of piping spools and consequent installation activities associated with the replacement program. While most of the tie-in works will be undertaken during shutdown conditions, the pre-planning works including fabrication and access requirements (e.g. scaffolding) will be undertaken prior to the outage events.

Vecta were engaged to execute the pipework replacement program for these work.

Objectives

The key objectives whilst completing the scope of works were:

  • Zero HSE incidents

  • Schedule monitoring and incorporation in to the overall shutdown time frames

  • Maintain or better cost targets

Scope of Works

Vecta Group Scope of Works included:

  • Final site measurements of existing pipework including closing lengths

  • Material procurement

  • Planning including work pack development

  • Offsite pipework fabrication, testing, coating and delivery to site

  • Scheduling, managing competing work scope interactions

  • Permit recipient process

  • Pre-shut access installation and modification during installation

  • QA and MDR finalisation

  • Practical Completion signoffs and handover

Delivery

Delivery included the site scanning of the existing pipework installations. This process verified the isometrics provided by the client and minimised the site weds during outage conditions.

Outcomes

Vecta Group self performed the site scanning requirements. This in turn verified the fabrication requirements. Off site fabrications was undertaken by one of Vecta’s alliance partners, with site installation be fully self performed by the Vecta Group. Using this strategic process, Vecta Group were able to minimise the site welding requirements and provide an installation schedule that fully complied with and significantly compressed the original duration allowed for by our Client.

The most significant outcome by the Vecta Group ws the reduction in site installation requirements enabling the Client to reduce the allowable outage event duration. Return to operations was earlier than planned.