E&I Engineering Support

Key Capabilities

  • Completions

  • Pre-Commissioning

  • PIMS CCMS

Overview

In November 2017, our Client, Australia’s leading energy infrastructure business, acquired a gas processing plant in east Victoria. This afforded our client remit to own, upgrade and operate the plant, which would process gas from offshore fields. As a fully operational plant, its capacity would be up to 68 TJ/d of natural gas, which is equivalent to 12% of current demand in Victoria.

Vecta were engaged to provide Electrical, Instrumentation and Controls (EI&C) engineering support during the critical phases of the gas plant upgrade, which were the mechanical completion, pre-commissioning and commissioning phases.

Scope

The scope included the following:

  • Executing pre-commissioning activities (I&C) and accountable for maintaining I&C teams productivity and adherence to schedule.

  • Managing, instructing and supervision a team of 18

  • Instrument Technicians, including management and provision of test gear and consumables.

  • Provision of technical advice during testing and ensuring all work is carried out in a safe and reliable manner.

  • Preparing EI&C Pre-commissioning specifications and procedures.

  • Estimating and scheduling EI&C Pre-commissioning task durations.

  • Completing full review of the EI&C portion of the PIMS CCMS.

  • Subsystem walkdowns with construction team and accepting subsystem MC handover.

  • Accepting MC ITRs and confirming punch item closeout and status from construction team.

  • Completing Pre-commissioning ITR checksheets and punch item closeout.

  • Preparing sub-systems dossiers for pre-commissioning handover.

Challenges

  • Compressed commissioning schedule due to construction delays and environmental disturbances in the region.

  • Dynamic critical path that led to ever-changing priorities.

  • Incomplete data and missing assets in PIMS CCMS.

Solutions

As a Major Hazard facility, pre-commissioning and commissioning activities were required to be risk assessed and managed as necessary, which was a considerable challenge with a moderately sized team.

Subsystem prioritisation and a working knowledge of punch items that may hinder progress were also crucial elements in the methodology employed to advance commissioning activities within a compressed timeframe.

Outcomes

There were no incidents or injuries that occurred under Vecta Group E&I supervision.

The Client was able to meet their Customer’s demand.

Previous
Previous

Coal Seam Gas Central Processing Plant FEED Study

Next
Next

FEED Study (Manufacturing Facility)