E&I Supervisor Support
Overview
In November 2017, our Client, Australia’s leading energy infrastructure business, acquired a gas processing plant in east Victoria. This afforded our client remit to own, upgrade and operate the plant, which would process gas from offshore fields. As a fully operational plant, its capacity would be up to 68 TJ/d of natural gas, which is equivalent to 12% of current demand in Victoria.
Vecta were engaged to provide Electrical & Instrumentation (E&I) supervisory support during the critical phases of the gas plant upgrade, which were the mechanical completion, pre-commissioning and commissioning phases.
Scope
The scope of work included the following:
Co-ordination and field supervision of craft completing pre-commissioning & commissioning activities
Test pack development including document revision control
Procedure and Notice of Energisation (NOE) certificates preparation
PIMS Completions & Commissioning Management Software (CCMS) / database and ITR reviews
Isolation list and PTW development including SWMS and JSEAs
Liaising with engineering for technical query close-out
Reviewing as-built E&I drawings
Daily reporting to management
Attending daily meetings for completions, commissioning and SIMOPS
Facilitating daily pre-starts, weekly team toolbox and return to work reset
Challenges
Compressed commissioning schedule due to construction delays and environmental disturbances in the region
Dynamic critical path that led to ever-changing priorities
Incomplete data and missing assets in PIMS CCMS.
Solutions
As the critical path of pre-commissioning and commissioning phases proved to be dynamic, Vecta Group emphasised the importance of monitoring subsystem priorities and constant communication
between supervisors and commissioning management in order to ensure the craft was directed to the correct work fronts.
The experience and problem-solving capabilities of Vecta Group supervisors was also a critical factor in determining the cause of and rectifying technical issues that had arisen during pre-commissioning activities such as loop testing.
Outcomes
There were no incidents or injuries that occurred under Vecta E&I supervision.
The Client was able to meet their Customer’s demands.