Instrument Air System Upgrade
Key Capabilities
Project Management
On-site Installation
Self-Perform – Electrical, Instrumentation and Mechanical
Specialist subcontractor engagement
Commissioning
Overview
Our Client operates the Dandenong City Gate which has an existing instrument air supply arrangement.
To guarantee future supply a new dedicated air package is required within the LNG facility
The Proposed package will include dedicated duty stand-by air compressors with wet air receivers, desiccant driers and oily water collection tank and a large volume dry air receiver with capacity to supply the LNG facility and for Dandenong City Gate.
Scope
The scope including:
•Mechanical equipment installation
•Pipework suppl and install
•Electrical and instrumentation works
•Commissioning
Delivery
Vecta Group self performed:
Project management
Procurement
Construction – structural, piping, mechanical, electrical and instrumentation
Commissioning
Civil works were subcontracted.
Vecta executed the works without incident commencing with the civil works (which included bored piers), pipework supply and fabrication, electrical and instrumentation works for the complete installation through to pre-commissioning, testing, commissioning and operating integrity.
Challenges
Significant timeframe deadlines were imposed on the project driven predominantly by market conditions. In a collaborative approach between Vecta and our Client, the project was delivered ahead of the aggressive target without incident.
Outcomes
Vecta are proud that the project was delivered for our client successfully, on time and budget without incident.